HS2 starts first M-shaped cut and cover tunnels

Aaron Morby 3 years ago
Share

French engineering specialist Matière has started installing the first of five planned ‘green’ cut and cover tunnels on the HS2 project.

Design and offsite fabrication more than halve the amount of carbon embedded in the structure
Design and offsite fabrication more than halve the amount of carbon embedded in the structure

HS2 engineers have adopted a twin arch ‘M’ shape structure design, which is more efficient than the standard box structure, reducing the amount of concrete used.

Segments are being manufactured offsite in a factory in Derbyshire for the 2.5km Chipping Warden green tunnel in Northamptonshire.

This lighter-weight modular approach is expected to more than halve the amount of carbon embedded in the structure. It also requires fewer workers and equipment on site.

Applying lessons from the construction of the latest French high speed lines, the off-site approach was developed by main works contractor, EKFB – a team made up of Eiffage, Kier, Ferrovial Construction and BAM Nuttall.

Five different concrete precast segments are slotted together to achieve the double arch – one central pier, two side walls and two roof slabs. Each arch is the height of a London double-decker bus.

More than five thousand giant concrete tunnel segments will be made by Stanton Precast in Ilkeston before being assembled by Matière.

The completed tunnel will then be covered by earth, with trees, shrubs and hedgerows planted to fit in with the surrounding countryside.

2.5km long concrete slab being poured ahead of tunnel arch installation

EKFB’s Project Manager, Jeremie Martin, said: “This three-year construction programme will benefit from off-site manufacturing making the green tunnel build more efficient than the traditional on-site building method.

“The HS2 green tunnels are a first of its kind in the UK. We have designed them as a twin arch ‘M’ shape which is more efficient than the standard box structure, reducing the amount of concrete required, which is a great example of how innovative engineering design can reduce carbon impact.”

Tunnel construction is expected to be complete in 2024.

Similar green tunnels will also be built at nearby Greatworth as well as Wendover in Buckinghamshire and Burton Green in Warwickshire, stretching for a combined total of more than four miles.

The tunnels will all have specially designed ‘porous portals’ at either end to reduce the noise of trains entering and exiting the tunnel, along with small portal buildings to house safety and electrical equipment.

 

Latest news

Resi developer Sheen Lane heading for administration

Richmond based firm has a turnover of £50m
3 hours ago

Building safety act adding six months to delivery times

New approval gateways slow student room development programmes
2 hours ago

Five contractors win £550m airfield framework deal

MAG picks team for Manchester, Stansted and East Midlands airports
2 hours ago

Galldris bounces back to strong profits

South east civils specialist gets trading margin up to 11%
2 hours ago

Management buyout at Midlands contractor

Family business GI Sykes sold to management
2 hours ago

Taylor Woodrow wins Wolverhampton city centre revamp

£19m contract will last two-and-a-half years
2 hours ago

Morgan Sindall contracts league champion for second year

Kier ranks second in closely contested race between majors
1 day ago

New Year layoffs as Scottish modular house builder collapses

East Ayrshire Connect Modular falls into administration
1 day ago

Thames Water bidders day for £2.2bn reservoir scheme

Tenders to be invited in October for new Abingdon reservoir in Oxfordshire
1 day ago

Buckingham Plant Hire quits heavy kit market

Firm to sell fleet and focus on lighter, sustainable plant
2 days ago

Clients ‘ignoring building safety’ reforms

Clients still subjecting contractors to aggressive and sub-economic pricing
1 day ago

Castleforge plans expansion after £100m data centre deal

Investor moves into booming data centre market
1 day ago

Construction output growth drops to six-month low

Subcontractor rates rise at fastest rate for 18 months
2 days ago

Suir Engineering swoops for Scottish M&E contractor

Irish M&E firm launches UK expansion with Taylor & Fraser acquisition
2 days ago

Aggregates supply firm files administration notice

Ashville Aggregates and Concrete operates across London and South East
2 days ago

Plans in for 44-storey Manchester resi tower

Developer Glenbrook to appoint contractor this year
3 days ago

Briggs & Forrester names new engineering services MD

Will Newman replaces Ian Lawrence who steps down after eight years
2 days ago

Morgan Sindall bags Salford Uni acoustics building

Planning submitted for Acoustics Building at Crescent Innovation area
2 days ago

Lambeth to release six sites for £250m homes plan

Call for development partner to deliver 450 mixed tenure homes
2 days ago

Adrian Speller joins brother as joint MD of Midlands builder

Speller Metcalfe boosts senior leadership team
3 days ago

Winner unveiled for £2.9bn aqueduct revamp

Construction costs for Haweswater Aqueduct rise to £2.9bn from £1.75bn
5 days ago

Fortem and Equans face fight for £3bn housing upkeep deal

Birmingham City Council aims to sign new 10-year deals for four regions
3 days ago

Lendlease strikes deal to sell UK construction arm for £35m

US private equity firm Atlas to finalise purchase deal by summer
7 days ago

Hercules to offload suction excavator arm

Fleet of 30 trucks generates around £5m revenue a year
3 days ago

Tarmac trials new technique to cut concrete road noise

Quieter trips for drivers and longer-lasting roads
3 days ago

HS2 set for “fundamental reset” to lower construction costs

New chief executive promises action after latest project update
1 week ago

Solar panel installer fined £120,000 after roof fall

Court hears how employee broke his leg in fall
1 week ago

Network Rail chief Andrew Haines knighted

Thin pickings for construction in this year's New Year Honours
1 week ago

Staff stunned as engineering consultancy Clarkebond closes

Firm was only bought three months ago by rival Independent Design House Group
2 weeks ago

Vistry issues third profit warning in three months

Profit expected to fall £50m below forecast due to delayed completions
2 weeks ago

Contractor services