Delays and cost hikes hit Balfour Highlands rail job

Grant Prior 3 years ago
Share

Balfour Beatty has been forced to push-back the completion date of its £16m contract to repair the UK’s highest railway.

The Scottish Government’s Highlands and Islands Enterprise (HIE) agency has confirmed the Cairngorm furnicular will not reopen until the “second half of 2022.”

The railway at the ski resort was due to reopen early next year following strengthening work on the 1.9km viaduct that supports the track.

Balfour began work in April 2021 but delays have arisen due to “technical challenges associated with designing and implementing effective solutions to an existing structure, as opposed to a new build.”

Work has also been hampered by the impact of Covid and extreme weather including blizzard conditions in the spring.

HI added that “extra effort has also been required to source vital construction materials that are currently in short supply across the UK.”

HIE interim chief executive Carroll Buxton said: “We’ve always been upfront in describing the reinstatement programme as one of the most complex and difficult civil engineering projects in Scotland.

“As well as managing technical challenges, the team has to take great care to protect the mountain environment, and deal with difficult terrain and extreme weather conditions that can quickly become hazardous.

“The original schedule was very ambitious, even without the impacts of the pandemic lasting as long as they have and before the more recent problems in sourcing construction materials of suitable quality.

“With limited time available to complete these works before winter, postponement has become inevitable.”

The funicular was built by Morrison Construction and opened in 2001 but was taken out of service in 2018 after an engineers’ inspection identified structural defects that raised safety concerns.

Buxton said: “We’re now working with our designers and contractors on a revised schedule for the remainder of the project.

“Harsh mountain conditions mean that all work will need to halt over winter and resume next spring. To ensure safety, there also needs to be a period of testing and certification at the end of the programme, so our current expectation is that the funicular can be relaunched in autumn 2022.

“Clearly, a longer timescale will also have a financial impact. We’ll be reviewing costs very carefully and will publicly confirm a revised budget as soon as it’s possible to do so.”

HIE has also approved up to £780,000 for an extensive refurbishment of the Ptarmigan building that sits on the plateau and includes the UK’s highest restaurant, a shop, exhibition space and viewing platforms.

Following competitive tender, resort operator Cairngorm Mountain (Scotland) Ltd (CMSL) has awarded a contract for the first phase of the Ptarmigan works to Simpson Builders Ltd, based in Beauly. The refurbishment is due to start at the end of August and be completed by the end of 2021.

 

Latest news

Wates wins former Daily Mail printworks transformation

British Land advances major cultural venue at London’s Canada Water
18 hours ago

Mace poaches Ramboll chief to be Head of Engineering

Martin Feakes will develop civil and structural engineering offer at Mace
17 hours ago

Subcontractors form alliance for major civils jobs

Trio of specialists join forces to collaborate and offer Tier 1 contractors a turnkey solution
21 hours ago

Fear of supply chain failures boosting collaboration

Procurement survey also reveals project bank account use is rising
21 hours ago

Wates sets up business to target 160,000 mouldy social homes

Healthy Homes service will be offered to social landlords across England
22 hours ago

Higgins wins £75m Peabody Passive House job

Latest phase of Deptford Landings to start construction
21 hours ago

Contractors and unions agree Sizewell C working deal

New deal offers improved sick pay and parental leave over Hinkley Point deal
1 day ago

Competition chiefs win legal fight for more construction raids

High Court rules CMA officials can raid a domestic property as part of investigation
2 days ago

More Osborne companies file administration notices

Three more divisions lodge notices with court
2 days ago

McLaren wins multi-storey urban logistics contract

South London win with British Land is pioneering urban logistics hub
2 days ago

Big social housing schemes at risk over funding uncertainty

Housing associations warn uncertainty over public funding beyond 2026 is curbing new schemes
2 days ago

Kier wins Worcestershire town centre renewal

Firm secures Bromsgrove commercial and cultural hub project
2 days ago

BAM signs Kent school contract at £42m

Sevenoaks school rebuild signed off at £8m more than first estimates
2 days ago

RG Group signs £121m Newcastle rental homes job

Developer Olympian Homes advances 519 flats plan at Pottery Lane site
5 days ago

Geoffrey Osborne files administration notice

Contractor in talks to save parts of the business
5 days ago

Winners named for £260m Manchester Uni framework

B&K, Henry Bros, Graham, Robertson and Vinci among new line-up
5 days ago

Shed specialist Benniman rides out market lull

Worcestershire warehouse builder says industrial and logistics work is picking up again
5 days ago

Another contractor cleared after high profile immigration raid

Adana Construction employees were working legally on site swooped on by Home Office
5 days ago

McAleer & Rushe wants to meet new London suppliers

Contractor holding Meet the Buyer event in London: Register now
5 days ago

McAlpine signs £500m Broadgate dual towers deal

Work to start on iconic 36-storey and 21-storey towers
6 days ago

Worker rescued from collapsed four metre deep trench

Fire crews take six hours to save trapped builder near Blackwall Tunnel
6 days ago

Gove puts another major building scheme on hold

Secretary of State starts another planning fight after M&S defeat
7 days ago

Greenwich University tenders £300m framework

Up to five firms will carry out upgrade and newbuild work at three campuses
6 days ago

Work starts on Manchester 26-storey Obsidian tower

Contractor Domis starts Salboy's 10th Manchester scheme in seven years
6 days ago

Race for £1.3bn West Midlands social homes framework

The Community Housing Group reboots tender race for new build housing
6 days ago

Delancey submits £400m King’s Cross lab plans

200,000 sq ft lab/office project will be built above railway and tube tunnels just 4.5m below
7 days ago

Winners revealed for £150m fire safety framework

New deal will help organisations comply with the Building Safety Act
6 days ago

Sellar plans £500m City tower next to Walkie-Talkie

Consultation starts on London 60 Gracechurch Street tower
7 days ago

Severfield ends year on high with record order book

Orders top £500m with strong future pipeline of opportunities ahead
7 days ago

Second senior director exits National Highways

Commercial director Malcolm Dare set to move on to new role
7 days ago

Contractor services