Crossrail parts company with Costain Skanska at Bond Street

Grant Prior 4 years ago
Share

Costain/Skanska joint venture’s troubled Crossrail contract at Bond Street Station has been ended early.

Crossrail said the mutual decision was made “due to the volume of work remaining and the number of people required on site to complete the station” in a post-Covid world.

One site source told the Enquirer: “Word went around the job on Tuesday that this was happening and that Wednesday would be their last day.”

The Enquirer understands that Crossrail and the contractors were in discussions until midnight to agree terms of the split.

The problem job is the only one of ten central London Crossrail stations that is not yet ready for the trial running of trains.

Continued productivity issues on the site have seen it lag behind other stations.

Crossrail bosses hope to have the central section between Paddington and Abbey Wood finally up and running from summer 2021.

The £18bn project was originally due to open in December 2018.

The latest project update earlier this month said: “All central section stations, except Bond Street, have now been certified as ready to support Trial Running – Bond Street will be ready to support Trial Running by the end of July.”

The Costain/Skanska joint venture started work at Bond Street in February 2013 on a contract originally valued at £200m which was expected to be completed by February 2017.

A Crossrail Ltd spokesperson said: “In the light of Covid-19, we have been reviewing and re-structuring any works that are essential to opening the railway and to ensure we complete the Elizabeth line in the most effective and efficient way.

“This includes at Bond Street which is uniquely affected by the post-Covid world due to the volume of work remaining and the number of people required on site to complete the station.

“Over the last few weeks Crossrail Ltd has been in discussions with Costain Skanska Joint Venture (CSJV) to agree a way forward for Bond Street.

“As a result, Crossrail Ltd and CSJV have mutually agreed to conclude the existing contract as of midnight on 24 June and will work together to ensure a safe and effective transition. Crossrail Ltd will be putting in place new arrangements to complete the works which largely relate to fit-out and testing and commissioning activity.”

“Despite the significant challenges COVID-19 brings our focus remains on doing everything we can to open the central section between Paddington and Abbey Wood as soon as possible and the earliest possible opening for Bond Street.”

A CSJV spokesperson said: “In the light of COVID-19, Crossrail has been reviewing and re-structuring any works that are essential to opening the railway and to ensure it completes the Elizabeth line successfully.

“This includes at Bond Street which is uniquely affected by the COVID-19 crisis, due to the number of operatives required on site to complete the station.

“Crossrail will now consider plans for any future works in a post COVID-19 environment.

“As a result, Crossrail and CSJV have mutually agreed to conclude the joint venture’s works under the existing contract as of midnight on 24 June and will work together to mitigate costs and to ensure a safe and effective transition.”

Crossrail will complete the works in-house which largely relate to fit-out and testing and commissioning activity.

The Enquirer understands Engie are also now on site to carry-out “care and custody and security arrangements” at Bond Street.

CSJV continues to work with Crossrail as main contractor at Paddington where arrangements are unchanged.

 

 

Latest news

Plant bosses blast “inflexible” police over road bans

Officers spotted outside sites and depots monitoring movements of large kit
6 hours ago

Construction recovery rained-off in first quarter

Sharp rise in commercial orders offers hope for Summer recovery
12 hours ago

Skanska tops April contract wins ranking

London office and data centre projects lift Skanska
13 hours ago

Modular builder TopHat managing director departs

Andrew Shepherd leaves Goldman-Sachs backed volumetric business
1 day ago

Balfour wins major Rolls-Royce Derby campus expansion

Masterplan involving 14 building projects will take eight years to complete
12 hours ago

Graham nets £60m stands revamp at Lord’s

Construction to start this summer at the home of cricket
1 day ago

Contractors face mental health quiz to win work

Prequalification specialist pushing for mental health questions in assessments
13 hours ago

Building boss banned for covid loan abuse

Latest investigation into £50,000 Bounce Back Loan
12 hours ago

Ready mix concrete giant files administration notice

Mixit Concrete Limited lodges court notice
1 day ago

Dual student towers plan for Birmingham Gun Quarter

Sama Investments goes to public consultation on 50-storey scheme
2 days ago

15 win £3.5bn Eastern Route Partnership railway deal

Amco, BAM, Morgan Sindall and Story among winners on Eastern Routes Partnership
1 day ago

Expanding Caddick Group tops £500m turnover

Construction drives revenue growth and returns to profit
2 days ago

Structure Tone returns to profit

Contractor confident about prospects in London fit out and refurb market
2 days ago

33 firms secure spots on £3.6bn Northumbrian Water framework

Applebridge, Galliford, Esh and Keltbray may
1 day ago

Construction boss in court over dodgy van deals

Suspended jail sentence after court hears how millions in unexplained payments went through Leeds contractor
2 days ago

Development firm fails hitting London building team for £2.6m

Luxury flats builder Ant Yapi was contracted to redevelop Westminster Tower site
3 days ago

Government set to fund £1bn final HS2 London tunnel drive

Final tunnel drive to be taxpayer funded upfront with cash recouped later
2 days ago

Amazon fires up Big-Box market with £500m job

Next generation triple floor super-shed to be built near Northampton
3 days ago

Stricken road sweeper specialist rescued

Parts of hire specialist Go Plant bought out of administration by Sweeptech
3 days ago

Costain highways lead joins Buro Happold

Paula Gough appointed to UK Development Director for Infrastructure
3 days ago

G&H Group lands £20m+ M&E package from JJ Rhatigan

100-strong specialist team to start on West London site next week
3 days ago

Bidding open for £800m professional services deal

Procure Partnerships encourages SMEs to bid with 9 regional lots
3 days ago

Construction buyers see fastest growth for 14 months

Commercial building work leads the way in April
3 days ago

Go Modular Technologies files administration notice

Southampton bespoke volumetric specialist employs around 60 staff
3 days ago

Cladding firm went down owing supply chain £7.7m

Debts revealed at Everton stadium cladding contractor Alucraft Systems Ltd
4 days ago

Rydon dogged by legacy fire safety remediation costs

£19m spent on fire safety remediation work to date
4 days ago

Carpenter killed by falling timber frame panels

Court fines specialist contractor £8,000 after site tragedy
1 week ago

Trio of builders win King’s Award for sustainability

Henry Brothers, Willmott Dixon and ZED Pods recognised for sustainability
3 days ago

Kent police seize huge haul of stolen site tools

Hunt for power drill fitted with tracker busts tool theft ring
3 days ago

Robertson names new Northern construction chiefs

Ian Phillips promoted and Ricky Brown joins from Morgan Sindall
4 days ago

Contractor services